NODESCRIPTION FINISH RECOMMENDATIONS
1 38 48 or 60 dia UNIVERS post
Plasticcoated or Galvanised
1 per end 1 per corner 1 per tensioning point
every 25 m 1 intermediate post every 250 to 300 m
2 38 or 48 dia strut
For fences of nominal height 2 m only
1 per end 2 per corner and tensioning point
3 38 or 48 dia spacer bar
For fences of nominal height 2 m only
1 per end 2 per corner and tensioning point
4 38 or 48 dia end cap Plasticcoated or aluminium alloy 1 per strut 2 per spacer bar
5 38 48 or 60 dia collar clamp fastenings
Plasticcoated 38 mm dia or
stainless steel 48 and 60 mm dia
1 per strut 2 per spacer bar
1 per tension wire end 1 per tensioning point
6
Guying kit cable clamp 33 mm dia cable
1x No 3 strainer junction plate M6 stainless steel screws and
bolts
1 per spacer bar
7 No 3 or 4 strainers
Plasticcoated or galvanised
1 per tension wire based on the recommended number
of rows at each corner
end or tensioning point
8 29 dia tension wire Based on the recommended number of rows and the length
9 Binding wire Approx 25 m for 25 m of fencing
10 UNIVERS staples Stainless or galvanised steel Number of staples based on fence height
11 UNIVERS staplerFor attaching staples to posts
C – Install a
tensioning post
every 25 m.
At corner junctions,
install a corner
post with spacer
bars and guy wires.
1
5 7 8 6
4
3
1
5
4
2
A – Install the f irst post
with 1 strut.
1
2
4
5
C – Install a tensioning
post every 25 m.
At corner junctions,
install a corner post
with 2 struts.
10
11
D – Attach the mesh with
UNIVERS staples
using the UNIVERS stapler.
10
11
D – Attach the mesh with
UNIVERS staples
using the UNIVERS stapler.
For fences < 2 m
Installation with struts
For fences ≥ 2 m
Spacer bars + guy wires recommended
A – Install the end post
using a spacer bar
and guying kit.
6
3
4
5
1
8
7
B – Install intermediate posts
every 2.5 to 3.00 m.
1
B – Install intermediate posts
every 2.5 to 3.00 m.
1
INSTALLATION PROCEDURE FOR UNIVERS + AXIAL
®
, ARIZONA AND BASTILLE
®
PARC POSTS